E.ON HEATING, HÄNDELÖVERKET, Heating and power plant, Oil burners

E.ON HEATING, HÄNDELÖVERKET

Project details: Analysis and review of functional descriptions, applications and logic. The review revealed about 50 action items in applications and controls. After establishing the action items, control and adjustments were initiated with good results. The project resulted in fuel reduction from 300-400³/month to the current 50-150 m³/month. In connection with the project the bottom ash handling system was rebuilt, which also contributed to the reduction.